TO DO Remove URS from slide
Continued and expanded partnerships (CLC, CWU, WTI, wildlife monitoring, agencies)
Engineering changes/issues resulted in additional analyses being completed, etc. (snowshed, design speed, slope stability, excess fill removal, temporary use of recreation areas, etc.)
SAC CP3. – Took 8 months to get to pre-CP3 (after consultants on board, and 14 months since PA adopted. The additional time taken overall, has resulted in quality and thoroughness in our analyses, as well as continued collaboration
106 compliance, meeting with tribes
Mitigation Planning underway (in addition to wetlands, have recreation, 106, etc.)