Dozens of meetings over 5 years
Dozens of meetings over 5 years
Implementation Plan Completed (Dec ’07)
- Ownership of screening facilities, long term O&M
- Consolidation Plan (Anderson, Reed, Hatfield to MWDA)
- Initial goal of 6 cubic feet per second dedicated to in-stream flow
- In-stream flow improvements continue until Steering Committee agrees all reasonable actions implemented
Fish screen and passage work planned for fall ’08
- Barnes Road, Keach/Jensen, MWDA (& Consolidated)
Conservation projects planned for ‘08 and beyond
- Pipe Menastash Water Ditch Association
- Sprinkler Conversions
Notes:
Implementation Plan is on our website at kccd.net